Wind Power Dominates Kenya's New Generation Mix as Coal Phase-Out Accelerates
Energy & Transport

Wind Power Dominates Kenya’s New Generation Mix as Coal Phase-Out Accelerates

Wind power has emerged as the dominant technology in Kenya’s new electricity generation pipeline for the remainder of the decade, with three major projects totalling over 500 megawatts under active development and the government having definitively shelved its long-contested coal power ambitions. The shift, confirmed in Kenya’s updated Least Cost Power Development Plan published in May 2026, marks the culmination of years of advocacy by climate campaigners, shifting economics that have made wind energy unambiguously cheaper than coal in the Kenyan context, and growing pressure from international development finance institutions to align with Paris Agreement-compatible pathways.

Energy CS Davis Chirchir was unequivocal when presenting the updated plan to the Cabinet. “Coal is not in Kenya’s future. It never was a good fit for a country with the geothermal, wind, and solar resources we have. The question now is how fast we build out what we know works,” he told journalists. The statement drew immediate praise from environmental groups including the Kenya Climate Action Network and a measured welcome from the World Bank, which has conditioned a $300 million development policy loan on Kenya’s continued alignment with clean energy commitments.

Lake Turkana and the Northern Wind Corridor

The Lake Turkana Wind Power (LTWP) project in Marsabit County remains the cornerstone of Kenya’s wind strategy. With its original 310 MW from 365 turbines having operated successfully since 2019, the project’s developer — a consortium including Aldwych International and KLP Norfund Investments — received government approval in March 2026 to proceed with a 150 MW expansion that will add 89 new turbines on the eastern shore of the lake. The expansion, financed through a mix of development finance from the European Investment Bank and project refinancing of the original facility, is scheduled for commissioning by mid-2028.

The LTWP site benefits from the channelling effect of the Turkana corridor — a geographic feature that produces consistent, high-velocity winds averaging 11 metres per second, among the strongest and most reliable wind resources on the African continent. Capacity factors at the site consistently exceed 55 per cent, compared with a global onshore wind average of approximately 35 per cent, making the levelised cost of electricity from LTWP expansion one of the lowest of any new generation source in Kenya’s planning period.

Two additional wind projects are in advanced development. The Kipeto Wind Energy Centre in Kajiado County, already partially operational at 100 MW, is adding a 60 MW second phase expected online in early 2027. And a new greenfield project, the Meru Wind Farm proposed by a Kenyan-Danish joint venture, is targeting 120 MW in the highland zone north of Meru town where resource assessments have recorded wind conditions comparable in quality to the Turkana corridor.

Coal’s Definitive Exit

The Lamu Coal Power Station — a 981 MW project that was for years among the most contentious infrastructure proposals in Kenya — has been formally removed from the power development plan after years of legal challenge, community resistance led by the Save Lamu campaign, financing withdrawals by major international banks, and ultimately a 2021 National Environmental Tribunal ruling that its environmental impact assessment was unlawful. Although proponents attempted several times to revive the project with modified configurations, the 2026 LCPDP closure marks what planners and campaigners alike describe as a final administrative conclusion.

The Amu Power Company, which held the Lamu coal licence, has not publicly responded to the plan’s publication. Government sources say the company’s remaining contractual claims are being settled through a confidential negotiation process. The land that had been earmarked for the power station site is being considered for a solar-plus-storage facility under a new competitive tender expected to launch in 2027.

The coal phase-out aligns Kenya with a regional trend: Uganda definitively cancelled its proposed Kabale coal plant in 2024, and Tanzania has redirected its own power development plan toward gas — which, while a fossil fuel, carries substantially lower emissions intensity than coal and serves as a transition fuel in the EAC’s larger, less renewable-rich electricity markets.

Grid Integration and Storage

The accelerating share of variable renewable energy — wind and solar combined are projected to reach 25 per cent of Kenya’s installed capacity by 2028 — is creating new grid management challenges. The Kenya Electricity Transmission Company (KETRACO) has been tasked with developing a grid flexibility investment plan, including battery energy storage system procurement at strategic nodes and the enhancement of interconnection capacity with Uganda and Tanzania to enable renewable export during surplus periods and import during low-generation hours.

A 50 MW grid-scale battery storage facility at Olkaria, co-located with the geothermal complex, has been approved as a pilot under a competitive solicitation process. The project, expected to be financed through a combination of Green Climate Fund concessional finance and private equity, will provide frequency regulation and spinning reserve services — functions currently performed by diesel peakers whose operating hours are expected to decline sharply as the wind-geothermal combination provides more consistent baseload and cycling capability.

For a country that less than five years ago was still debating whether to build a coal plant, Kenya’s 2026 energy trajectory represents a genuine strategic transformation — one that places it at the forefront of Africa’s clean energy transition and creates an industrial foundation well suited to competing for the green manufacturing investment that the continent is expected to attract over the coming decade.

Read More
Kenya Launches National EV Charging Network with 200 Stations by 2027
Energy & Transport

Kenya Launches National EV Charging Network with 200 Stations by 2027

Kenya’s Ministry of Energy and Petroleum has unveiled a national electric vehicle charging infrastructure programme targeting 200 publicly accessible charging stations across the country by the end of 2027, in what officials describe as the most comprehensive EV infrastructure policy commitment made by any sub-Saharan African government to date. The programme, announced by Cabinet Secretary Davis Chirchir in a policy statement to Parliament on 18 June 2026, combines direct government capital investment, private sector franchise licensing, and a regulatory framework developed in close consultation with the electric mobility industry.

“Kenya has set a target for 30 per cent of new vehicle sales to be electric by 2030. That target is meaningless if drivers cannot charge their vehicles,” Chirchir said. “The charging network we are building is the enabling infrastructure — the road beneath the road — that will make EV adoption rational for ordinary Kenyans, not just for environmentally committed early adopters.”

Network Design and Station Locations

The 200 stations will be distributed across four tiers. The first tier covers the Nairobi metropolitan area, where 60 stations will be installed at a combination of public car parks, shopping centre forecourts, and government facility grounds in Nairobi, Kiambu, Machakos, and Kajiado counties. The second tier targets the Mombasa-Nairobi highway corridor, with DC fast chargers capable of delivering an 80 per cent charge in 30 to 45 minutes installed every 50 kilometres — addressing the range anxiety that highway travel creates for owners of smaller-battery vehicles common in the Kenyan market.

The third tier covers Kenya’s six other major urban centres: Kisumu, Nakuru, Eldoret, Thika, Nyeri, and Meru. Each will receive between five and 12 stations depending on population and projected EV uptake, with charging infrastructure co-located with existing fuel stations where site agreements can be reached. The fourth tier, explicitly developmental in character, targets 20 stations in county headquarters that currently have limited or no EV charging presence — including Garissa, Isiolo, Kitale, and Homa Bay — to signal that the EV transition is not limited to the urban middle class.

The Energy Regulatory Authority has published technical standards for the charging equipment, mandating compatibility with CCS2, CHAdeMO, and Type 2 AC connectors — the three standards that cover the overwhelming majority of EV models available in the Kenyan market, which includes growing imports of Chinese brands such as BYD, Changan, and MG alongside established Japanese and European electric models.

Financing and Private Sector Role

Government capital expenditure will fund the installation of the first 80 stations in tiers one and two, with a total public allocation of Ksh 4.5 billion across the 2026/27 and 2027/28 budgets. The remaining 120 stations will be financed and operated by private sector licensees under a franchise model, with the government providing a viability-gap subsidy per station of between Ksh 800,000 and Ksh 1.5 million depending on location tier.

Safaricom has already indicated its intention to integrate M-Pesa payment directly into the charging network’s mobile application, with a pilot underway at three Nairobi stations that allows drivers to initiate, monitor, and pay for charging sessions entirely through the M-Pesa super-app. The company is also evaluating a loyalty programme integration that would award Bonga Points per kilowatt-hour charged — a consumer incentive that Safaricom executives believe could meaningfully accelerate early EV adoption among the upper-middle-income demographic that currently leads uptake.

Kenya Power has been designated as the technical offtake partner for the network, responsible for metered supply connections and for ensuring that the charging stations receive power at the dedicated EV tariff — a new commercial category set at Ksh 15.80 per kWh, approximately 30 per cent below the standard commercial retail rate, in recognition of the predictable, schedulable nature of EV charging load that is beneficial for grid management.

Market Context and Challenges

Kenya’s EV market, while nascent by global standards, has been growing at a pace that surprised even optimistic industry forecasters. The Kenya Revenue Authority’s import data shows that 4,800 fully electric passenger vehicles were registered in Kenya in 2025, up from 1,100 in 2023 — a more than fourfold increase in two years. The government’s removal of import duty on electric vehicles in the 2023 Finance Act (the same bill that triggered the Gen Z protests before being withdrawn and subsequently replaced with a revised version) has remained in force and is widely credited as the primary demand driver.

Infrastructure challenges remain significant. The geothermal-dominated grid provides clean, cost-competitive power, but distribution reliability in some areas — particularly the peri-urban fringe where land for charging facilities is more available — remains a concern. Kenya Power’s technical losses of nearly 18 per cent represent wasted generation and create voltage instability that can damage fast-charger power electronics.

There is also the issue of the second-hand EV market. Most Kenyan buyers access vehicles through the used-import channel from Japan, and the availability of second-hand electric vehicles with degraded battery capacity has already generated consumer complaints. The Kenya Bureau of Standards is developing a battery health certification requirement for used EV imports, expected to be gazetted before the end of 2026.

Read More
Mombasa-Nairobi SGR Posts Record 8 Million Passengers in 2025
Energy & Transport

Mombasa-Nairobi SGR Posts Record 8 Million Passengers in 2025

The Standard Gauge Railway’s Madaraka Express passenger service between Mombasa and Nairobi carried a record 8.03 million passengers in the calendar year 2025, according to official figures published by Kenya Railways Corporation in June 2026. The figure represents a 22 per cent increase over the 6.6 million passengers recorded in 2024 and a near-doubling of the service’s 2021 numbers, cementing the SGR’s status as the most commercially successful long-distance rail operation in East Africa and one of the few post-independence Kenyan infrastructure investments to have demonstrably exceeded its demand projections.

Kenya Railways Managing Director Philip Mainga said the milestone validated the controversial decision to build the SGR, which has been a subject of persistent public debate over its Chinese loan financing and debt service implications. “Eight million Kenyans chose the train over the road last year. That is the clearest possible market signal that this service meets a genuine need and is meeting it well,” he said at a press conference at Nairobi Terminus in Syokimau.

What Is Driving Demand

Several factors have combined to push passenger numbers to record levels. Fares on the Madaraka Express remain broadly competitive with road transport when travel time, safety, and fuel costs are factored in — the standard economy seat from Nairobi to Mombasa was priced at Ksh 1,000 for most of 2025, with a first-class seat at Ksh 3,000, against a typical bus or matatu fare of Ksh 700 to Ksh 900 for a journey that takes five to eight hours by road compared with the train’s consistent four hours and thirty minutes.

Safety has been a particularly significant driver. Kenya’s road fatality statistics remain grim — the National Transport and Safety Authority recorded 3,891 road deaths in 2025, many of them on the Nairobi-Mombasa highway, which is one of the country’s most accident-prone corridors. The complete absence of fatal accidents on the SGR since its launch has created a strong safety premium in the minds of Kenyan travellers, particularly families with children and business travellers for whom reliability matters.

Tourism recovery has also contributed substantially. International arrivals to Kenya reached 2.9 million in 2025, their highest level since before the COVID pandemic, with coastal tourism — Diani, Malindi, Watamu, and Mombasa itself — accounting for a growing share. The SGR’s direct connection from Jomo Kenyatta International Airport’s Syokimau terminus to Mombasa’s Miritini station has made it the preferred option for organised tour groups, with several major European and North American tour operators now building SGR segments explicitly into their itineraries.

Operational Improvements and Service Expansion

Kenya Railways has, over the past two years, incrementally increased train frequency on the corridor. Daily services now stand at six return trips in each direction — up from four in 2022 — with a seventh added on Fridays, Sundays, and public holidays to handle peak demand. An eighth daily service is under consideration for introduction in the third quarter of 2026, contingent on the completion of crossing-loop upgrades at three intermediate stations that constrain scheduling flexibility on the single-track sections of the route.

Cargo revenue on the SGR has also grown, with dry containers from Mombasa Port to the Nairobi Inland Container Depot increasing by 14 per cent in 2025 to approximately 340,000 TEUs. The combined passenger and cargo performance has, for the first time, brought SGR operations — though not debt service — into positive operating territory. Kenya Railways posted an operating surplus of Ksh 2.1 billion in the 2025 financial year, the first time the corporation’s accounts have shown a positive operating result since the SGR commenced commercial operations.

The Debt Question

The operating surplus, while commercially significant, does not touch the central financial challenge of the SGR: the Chinese Export-Import Bank loan that financed construction, estimated to carry outstanding balances of approximately $4.7 billion when Phase 1 (Mombasa-Nairobi) and the completed sections of Phase 2 (to Naivasha) are aggregated. Debt service payments — principal and interest — have been the single largest line item in Kenya’s bilateral debt obligations for several years, and the IMF programme’s debt sustainability framework has flagged the SGR loans as a key vulnerability in the country’s overall fiscal position.

Treasury officials argue that the revenue trajectory established by the 8 million passenger year, combined with the cargo performance, creates a credible path toward a commercialised SGR that can service its own debt without budget transfers. Sceptics note that even at current revenue levels, the gap between operating income and debt service remains large — and that Phase 2 extension to Kisumu, indefinitely paused for funding reasons, leaves the network at an economically suboptimal truncation point in Naivasha.

For ordinary Kenyans, however, those macroeconomic debates are somewhat abstract. The queues at Syokimau on a Friday evening tell their own story: the Madaraka Express has become a national institution, and 8 million passengers in a single year is proof that when public transport is safe, punctual, and affordable, Kenyans will use it.

Read More
Electric Bus Pilot Launched on Nairobi-Thika Route by Matatu SACCO
Energy & Transport

Electric Bus Pilot Launched on Nairobi-Thika Route by Matatu SACCO

The Northern Commuter Transport Savings and Credit Co-operative Society — better known by its trade brand NorthLink — made history on 3 June 2026 when it placed the first fleet of fully electric passenger buses into commercial service on the Nairobi-Thika route, one of the capital’s busiest and most polluted transport corridors. The pilot, which involves 12 electric buses supplied by Chinese manufacturer Yutong and locally assembled battery modules from a partnership with Nairobi-based BasiGo, represents the most significant step yet in the practical decarbonisation of Kenya’s matatu and bus sector.

NorthLink Chairman David Ngunjiri said the SACCO had spent two years preparing for the transition, including sending a delegation to Shenzhen to evaluate Yutong’s transit solutions and working with BasiGo’s engineers to ensure that the battery management systems could operate reliably under Kenyan road conditions, which include significant altitude variation between Nairobi and the Thika plateau.

“We have been carrying passengers on this route for 22 years. Our members know every pothole, every traffic jam, every school rush. We know exactly what a bus on this corridor needs,” Ngunjiri told reporters at the launch event at the Bus Station in downtown Nairobi. “These electric buses meet every one of those requirements — and they cost us 40 per cent less to run per kilometre than our diesel fleet.”

The Vehicle and the Financing Structure

The 12 Yutong E12 buses on NorthLink’s service are 12-metre low-floor coaches with a range of approximately 300 kilometres on a full charge — more than adequate for the 48-kilometre Nairobi-Thika round trip that each vehicle typically completes four to five times per day. Air conditioning, USB charging points at every seat, and a passenger information display are standard on the NorthLink livery, differentiated from the SACCO’s existing diesel fleet to build brand recognition around the electric service.

Financing was structured through a green loan facility from Kenya Commercial Bank’s sustainable finance division, with a 15 per cent interest rate buy-down provided by a concessional guarantee from the African Guarantee Fund. The NTSA has, for the first time, applied a differentiated inspection and licensing regime for zero-emission PSVs, reducing the annual compliance cost for the electric buses by Ksh 85,000 per vehicle compared with diesel equivalents — a policy concession that the Kenya Bus Service Management Board lobbied for over 18 months.

BasiGo, the Kenyan e-mobility start-up backed by pan-African climate investment funds, provides the charging infrastructure at two purpose-built depots — one at the Thika end in Kenyatta Road and one at Ngara in Nairobi — and manages the battery lease arrangement under a pay-per-kilometre model that separates the battery cost from the vehicle purchase. BasiGo co-founder Jit Bhattacharya said the per-kilometre battery lease price had been set to ensure NorthLink’s total cost of operation was below diesel from day one. “We are not asking SACCOs to take a leap of faith. We have de-risked the economics so the decision is obvious,” he said.

Corridor Context and Passenger Response

The Nairobi-Thika route carries an estimated 180,000 passenger journeys daily across all modes, including matatus, standard buses, commuter taxis, and the recently extended commuter rail service. The corridor’s air quality has been a longstanding public health concern: roadside PM2.5 readings in Githurai, Roysambu, and Kasarani — the urban settlements the route traverses — consistently exceed WHO guidelines by a factor of three to five during peak hours, with diesel bus and matatu emissions a primary contributor.

Passenger response in the first weeks of operation has been enthusiastic, with social media posts and word-of-mouth generating waiting lists for the electric service despite NorthLink charging a Ksh 20 premium over standard diesel bus fares on the same route. The SACCO attributes the premium acceptance to perceived comfort, quieter cabin noise, and what Ngunjiri describes as the “pride factor” — a sense among younger Nairobi commuters, many of them shaped by the Gen Z civic awakening of 2024, of choosing a cleaner city.

Government Policy and Scale-Up Plans

The energy ministry’s new National EV Charging Network, also announced in 2026, provides further infrastructure support. However, for high-frequency transit operations, the SACCO model of dedicated depot chargers proves more practical than public network reliance. The National Transport and Safety Authority has signalled it will use the NorthLink data — covering energy consumption, charging cycles, brake wear, and passenger loads — to inform technical standards for the PSV electric vehicle category, which currently exists in regulation only in skeletal form.

BasiGo and NorthLink have already received expressions of interest from five other Nairobi SACCOs seeking to replicate the model on routes including Nairobi-Ngong, Nairobi-Kitengela, and the CBD-Westlands-Kikuyu corridor. If a further 60 electric buses enter service by end-2026, the combined fleet would represent a meaningful — if still modest — fraction of the approximately 7,000 buses estimated to operate in Greater Nairobi.

Read More
Kenya Pipeline Company Upgrades Mombasa-Nairobi Fuel Line to Boost Capacity
Energy & Transport

Kenya Pipeline Company Upgrades Mombasa-Nairobi Fuel Line to Boost Capacity

Kenya Pipeline Company (KPC) has completed a multi-year upgrade of its Line 1 pipeline running from the Kipevu Oil Storage Facility in Mombasa to the Nairobi depot at Embakasi, increasing the line’s sustained throughput capacity from 440 cubic metres per hour to 600 cubic metres per hour and adding three new intermediate pumping stations along the 450-kilometre route. The upgrade, which also involves lining 110 kilometres of the oldest sections of the pipe to address corrosion-related leakage losses, was completed in June 2026 at a total cost of approximately Ksh 28 billion.

KPC Managing Director Joe Sang described the project as the most significant investment in the pipeline’s physical infrastructure since the company commissioned Line 2 — the parallel high-speed line — in 2014. “Line 1 has been running since 1978. Parts of it are nearly 50 years old. The upgrade extends its operational life by at least 25 years and brings it to a standard where it can handle the growing fuel demands of not just Kenya but our landlocked neighbours who depend on the Mombasa corridor,” Sang told journalists at the Embakasi depot.

Strategic Importance in the Regional Fuel Supply Chain

The Mombasa-Nairobi pipeline sits at the heart of a fuel supply chain that serves not only Kenya but also Uganda, Rwanda, South Sudan, eastern Democratic Republic of Congo, and parts of Burundi and Tanzania — countries with a combined import volume that makes the Mombasa port-pipeline combination the most strategically consequential petroleum logistics asset in East and Central Africa. Any disruption to the pipeline’s throughput — whether through mechanical failure, vandalism, or scheduled maintenance — has historically caused immediate fuel supply tightening across the region, with price spikes and queues at petrol stations in Kampala and Kigali following within days of a Kenyan pipeline incident.

The 2023 and 2024 El Niño seasons created particularly difficult operating conditions, with several sections of the pipeline right-of-way in Tsavo affected by flash flooding that damaged protective berms and increased the risk of third-party interference. The lining works completed this year address the most vulnerable sections identified in a 2022 integrity survey commissioned following a major spill near Makindi that contaminated the Tsavo River and led to a Ksh 450 million environmental remediation liability for KPC.

Throughput data from 2025 showed the pipeline handled approximately 1.2 billion litres of refined petroleum products — petrol, diesel, kerosene, and aviation fuel — a figure that represents roughly 70 per cent of Kenya’s total liquid fuel supply (the balance arriving by road tanker, a more expensive and less efficient mode that KPC is explicitly trying to displace). At the upgraded capacity, the pipeline could theoretically handle up to 1.6 billion litres annually, providing a supply buffer that operators and the petroleum industry say will reduce the frequency of the supply crises that have periodically forced the Energy and Petroleum Regulatory Authority to intervene on pricing.

Automation and Leak Detection

Beyond the physical capacity upgrade, KPC has installed a new SCADA-based supervisory control and data acquisition system along the full length of Line 1, replacing the analogue monitoring equipment on the oldest sections of the route. The new system provides real-time flow and pressure data at 500-metre intervals, enabling the control room at Embakasi to detect and locate leaks within minutes rather than the hours that older monitoring allowed. The system is integrated with KPC’s emergency response protocols, including automatic valve closure upon anomalous pressure drop detection.

The Kenya Revenue Authority has been given read-only access to the SCADA throughput data as part of an anti-smuggling and fuel tax fraud initiative jointly developed with the Energy ministry. Petroleum tax evasion — which Treasury estimates costs the exchequer between Ksh 15 billion and Ksh 25 billion annually — has been a persistent problem along the pipeline corridor, and the real-time volumetric data is expected to significantly complicate the physical diversions that have historically evaded detection.

Extension Plans and Regional Ambitions

KPC is simultaneously advancing planning for the extension of its pipeline network to Uganda — the Eldoret-Kampala pipeline project that has been under discussion in various forms since the 1990s. A revised feasibility study, funded by the African Development Bank, is expected by the end of 2026, and KPC officials have indicated that the upgraded Mombasa-Nairobi line provides the foundational throughput capacity required to make the Uganda extension economically viable.

For the petroleum downstream sector, the upgrade also arrives at a moment of transition: Kenya’s long-term liquid fuel demand trajectory is uncertain given the government’s accelerating EV and clean cooking commitments. KPC’s own modelling projects that petroleum demand will continue growing at three to four per cent annually through 2035 before plateauing — meaning the upgraded pipeline will be fully utilised for at least the next decade regardless of the pace of energy transition.

Read More
Kenya's Rural Electrification Programme Connects 500 More Villages in 2026
Energy & Transport

Kenya’s Rural Electrification Programme Connects 500 More Villages in 2026

Kenya’s Rural Electrification and Renewable Energy Corporation (REREC) has confirmed the connection of 500 additional villages to the national electricity grid in the first half of 2026, bringing the total number of villages with grid access to approximately 12,400 — up from under 5,000 a decade ago. The accelerated pace of connection, funded through a combination of World Bank credit, African Development Bank grants, and the government’s Last Mile Connectivity Programme, is transforming daily life across some of Kenya’s most remote and historically marginalised communities.

“These are not statistics — they are dispensaries that can now refrigerate vaccines, schools that can run computers after dark, and mothers who no longer have to buy expensive kerosene for their children to study by,” said REREC Director General Joseph Njoroge at a briefing in Nairobi last month. “The grid is arriving in places where people genuinely thought it would never come.”

Where the Light Is Reaching

The 500 new villages span 34 of Kenya’s 47 counties, with the largest concentrations in the arid and semi-arid lands where population density and commercial returns have historically deterred private investment. Turkana County — Kenya’s largest and among its least developed — received 47 new connections in the current programme cycle, many of them in pastoral communities near the shores of Lake Turkana where diesel generation had been the only prior electricity source. Marsabit, Wajir, Mandera, and Tana River counties similarly feature prominently in the current tranche.

In the highlands and central counties, the focus has shifted from initial connection to quality and reliability. Kenya Power has, in parallel to REREC’s extension works, been investing in transformer upgrades and low-voltage network reinforcement to address the persistent voltage fluctuation problems that have frustrated businesses and households in areas connected in the early phases of Last Mile but never subsequently reinforced.

The Social Health Authority rollout has added fresh urgency to rural electrification. SHA-contracted health facilities are required to demonstrate a reliable power supply as a condition of their accreditation for reimbursement purposes — a provision that has made electrification a direct enabler of universal health coverage in rural settings. REREC reports that 63 health centres and dispensaries received connections as part of the 2026 programme, several of which had been operational for years without grid power.

Technology Mix: Grid and Off-Grid

Not all of the 500 villages are connected to the national high-voltage grid. In the most geographically isolated communities — those beyond economic extension distance — REREC has deployed minigrids powered by solar photovoltaic systems with battery storage, operating under a service delivery framework that provides electricity at nationally regulated tariffs rather than the premium pricing common in privately operated off-grid systems.

Some 68 of the new connections are served by solar minigrids, most of them in Isiolo, Samburu, and West Pokot counties. Each minigrid typically powers between 80 and 300 households, together with at least one community institution — a school, dispensary, or water pump. REREC has integrated Safaricom M-Pesa metering systems that allow households to pre-purchase electricity in daily or weekly tranches directly from their mobile phones, a feature that has dramatically improved revenue collection compared with earlier prepaid metering approaches.

The El Niño aftermath, which damaged roads and bridges across much of western and coastal Kenya in late 2023 and 2024, created logistical complications that delayed some 2025 programme targets into 2026. REREC and Kenya Power acknowledge that the pace of physical connection was disrupted by access difficulties in areas where roads were washed out, and that the 500-village figure partly represents catchup from the previous year’s shortfall.

Economic and Social Transformation

Field assessments from the Kenya Institute for Public Policy Research and Analysis, published in May, found that communities electrified under the Last Mile programme three or more years ago had experienced statistically significant improvements in school examination performance, small business revenues, and household income relative to comparable unelectrified control communities. Women entrepreneurs — particularly those running food processing, tailoring, and mobile phone charging businesses — were identified as the primary economic beneficiaries of reliable nighttime power.

The government’s target is to achieve universal household electricity access by 2030, a goal that requires connecting an estimated 1.4 million additional households beyond current coverage. At the current pace — accelerated by the expansion of geothermal supply giving the grid the generation headroom to absorb new load — that target is considered achievable, though funding continuity and the KRA’s tight fiscal environment under the IMF programme remain key risk factors.

For President Ruto, whose administration has staked significant political capital on the electrification agenda as a visible development dividend, the June announcement provides tangible evidence of progress ahead of a 2027 election campaign in which rural voter turnout will be decisive.

Read More
Nairobi Commuter Rail Expansion Reaches Ruiru and Juja, Easing Traffic
Energy & Transport

Nairobi Commuter Rail Expansion Reaches Ruiru and Juja, Easing Traffic

Nairobi’s long-beleaguered public transport system has taken a significant step forward with the formal commissioning of the northern commuter rail extension serving Ruiru and Juja — two of the fastest-growing peri-urban settlements on the outskirts of the capital. The service, which began commercial operations on 14 June 2026, carries passengers from Nairobi’s central Syokimau-linked corridor to refurbished stations at Ruiru town and the new Juja Farm halt, cutting journeys that can take up to two and a half hours by road during peak traffic to under 45 minutes by rail.

Kenya Railways Corporation Managing Director Philip Mainga described the opening as the single most consequential expansion to the urban rail network since the Syokimau terminal was rehabilitated in 2012. “We are connecting people who live 40 kilometres from the CBD but whose economic lives are in Nairobi. Every minute we save them on the commute is a minute they can spend working, studying, or with their families,” he told a crowd of several hundred commuters who turned out for the launch at the refurbished Ruiru station.

Infrastructure Investment and Service Design

The extension required Kenya Railways to rehabilitate approximately 38 kilometres of track on the former Nairobi-Nanyuki metre-gauge line, which had fallen into disuse for passenger traffic by the early 2010s. Works included the relaying of worn rail sections, the construction of two new sheltered platforms at Juja Farm and the upgrading of Ruiru’s existing station building, installation of modern signalling equipment compatible with the existing metropolitan rail management system, and construction of park-and-ride facilities accommodating 600 vehicles at Ruiru and 300 at Juja Farm.

The project was financed through a combination of a World Bank urban mobility loan facility that has also funded the Thika Road non-motorised transport lanes, a Ksh 3.1 billion government appropriation in the 2025/26 budget, and a commercial loan from Development Bank of Kenya. Total project cost came in at approximately Ksh 9.8 billion — substantially under the original estimate of Ksh 12.4 billion, a rare outcome in Kenyan infrastructure delivery that Treasury officials attributed to improved procurement oversight under the IMF programme’s public investment management conditions.

Services currently operate every 30 minutes during peak hours — 05:30 to 09:00 and 16:30 to 20:00 — and every 90 minutes at other times. A fleet of six diesel multiple units refurbished at Kenya Railways’ Nairobi South workshop handle the route, with fares set at Ksh 100 from Juja to Nairobi and Ksh 80 from Ruiru, payable through M-Pesa, credit/debit cards, or Safaricom’s Beba Card contactless transit token introduced across the metropolitan rail network in 2025.

Relief on the Northern Bypass and Thika Road

Traffic modelling by the Kenya National Highways Authority suggests the new service should divert between 8,000 and 11,000 private car trips per day from the Northern Bypass and Thika Superhighway during peak hours, reducing average vehicle speeds on those corridors — currently among the slowest in East Africa during morning rush hour — by an estimated 12 to 18 per cent. Matatu operators serving the Thika Road corridor have been less welcoming. The Matatu Owners Association of Kenya has petitioned the National Transport and Safety Authority to review the rail fares, arguing the subsidy implicit in the World Bank loan funding constitutes unfair competition with the privately operated public service vehicle industry.

The commuter rail expansion also intersects with Kiambu County’s spatial planning priorities. Governor Kimani Wamatangi has been a vocal advocate for transit-oriented development around Ruiru and Juja — two towns whose populations are estimated to have grown by more than 60 per cent since 2019, placing severe pressure on water, sewerage, and road infrastructure. The governor’s office is in discussions with the Kenya Railways Corporation and the Nairobi Metropolitan Area Transport Authority over zoning amendments to permit higher-density mixed-use development within 500 metres of both new stations, a model that has delivered affordable housing in Tatu City’s private development adjacent to the Ruiru orbit.

Looking Beyond Ruiru and Juja

Kenya Railways has confirmed that the next phase of the northern corridor — a proposed extension to Thika town — is under feasibility study, with a report expected by December 2026. Thika, home to a significant industrial base including the Thika Industrial Area and a growing tech and light-manufacturing corridor along the Eastern Bypass, would be a more commercially productive terminus than the current Juja Farm endpoint.

The Nairobi Metropolitan Area Transport Authority’s integrated transport plan, approved by Cabinet in 2025, envisages a comprehensive commuter rail network of 12 lines by 2035, with connections to the SGR at Syokimau, bus rapid transit corridors, and the proposed Nairobi Expressway feeder routes. The Ruiru-Juja opening is the first concrete proof of that vision becoming reality — and for tens of thousands of daily commuters from Kiambu County, it cannot come fast enough.

Read More
Kenya's Geothermal Capacity Expands to 1,200 MW, Powering 4 Million Homes
Energy & Transport

Kenya’s Geothermal Capacity Expands to 1,200 MW, Powering 4 Million Homes

Kenya has crossed a landmark threshold in its renewable energy journey, with installed geothermal generation capacity reaching 1,200 megawatts — enough to power an estimated four million homes and placing the country eighth in the global ranking of geothermal producers. The milestone, confirmed by the Energy and Petroleum Regulatory Authority in a June 2026 bulletin, was made possible by the commissioning of the final 105 MW phase of the Olkaria VI project in Nakuru County and the completion of new steam wells at the Menengai Geothermal Development Project.

Energy and Petroleum CS Davis Chirchir called the achievement a “structural turning point” for Kenya’s grid. “For decades, Kenya has talked about its geothermal potential. Today that potential is generating electricity for millions of Kenyans at a cost per kilowatt-hour that no imported fuel could match,” he said at a commissioning ceremony attended by President Ruto at the Olkaria complex in Hell’s Gate National Park. “This is climate action that also makes economic sense.”

Olkaria and Menengai: The Twin Pillars

Kenya Electricity Generating Company (KenGen) remains the dominant force in geothermal development, operating the Olkaria complex that now spans six distinct generating stations with a combined nameplate capacity of approximately 900 MW. The Olkaria VI expansion, financed through a $340 million concessional loan from the Japan International Cooperation Agency supplemented by KenGen’s own revenues, took four years to complete and involved drilling 38 new production wells to depths averaging 2,800 metres.

The Menengai project, developed through the Geothermal Development Company (GDC) in a public-private partnership model, has had a more complex history — years of steam disputes between GDC and the three independent power producers contracted to build surface plants delayed progress significantly. But with all three plants now commercially operational, Menengai contributes 105 MW to the national grid, and GDC’s chief executive Dr. Jared Othieno told a Nairobi energy conference last month that a Phase 2 drilling programme targeting a further 200 MW is already in the feasibility stage.

Geothermal now accounts for approximately 47 per cent of Kenya’s total installed generation capacity of roughly 3,900 MW, making it the country’s single largest energy source by far. Combined with hydro, wind, and solar, Kenya’s renewables share of installed capacity now exceeds 92 per cent — a figure that draws frequent admiration from international climate negotiators and positions Kenya as a genuine African model for green industrialisation.

Grid Reliability and the Distribution Challenge

The expansion of generation capacity has, however, thrown Kenya Power’s distribution network into sharp relief. Transmission bottlenecks between the Rift Valley generating cluster and major demand centres — particularly the Nairobi metropolitan area and the Coast region — mean that a significant share of available geothermal output cannot always reach end consumers when they need it most. Kenya Power reported in its latest annual results that system technical losses averaged 17.8 per cent in the financial year to June 2025, well above the regulatory target of 14 per cent.

The government is addressing this through the Least Cost Power Development Plan’s transmission investment programme, which includes a new 400 kV transmission line from Olkaria to Isinya in Kajiado County and a proposed high-voltage direct-current link to Mombasa. Both projects are in advanced procurement, with construction expected to begin before the end of 2026.

Rural electrification, accelerated through the Rural Electrification and Renewable Energy Corporation’s Last Mile Connectivity programme, has absorbed a growing share of the additional geothermal output. The 500 villages connected in 2026 alone — detailed separately in the rural electrification programme — are predominantly served by the expanded grid rather than stand-alone systems, making geothermal the de facto power source for millions of newly connected rural households.

Climate and Economic Significance

Kenya’s geothermal expansion arrives at a moment of acute global interest in firm, dispatchable renewable power. Unlike solar or wind, geothermal delivers consistent baseload generation around the clock regardless of weather conditions — a characteristic that has grown more valuable in the aftermath of the El Niño event that ravaged East Africa’s hydro reservoirs in 2023 and 2024. The Tana River hydro cascade, which once contributed nearly 40 per cent of Kenya’s grid power, is still recovering to pre-drought storage levels, making the geothermal buffer critical to grid stability.

Industrial consumers, including East Africa’s growing data-centre sector and the Athi River cement cluster, have cited the reliability and competitiveness of geothermal power as a key factor in their Kenya investment decisions. The average geothermal tariff paid to KenGen under its power purchase agreement with Kenya Power stands at around KES 6.90 per kWh — substantially below the cost of thermal generation alternatives and competitive even against large-scale solar on a firm-energy basis.

With another 500 MW of geothermal capacity in the exploration or early development pipeline, Kenya is on course to surpass 1,700 MW by 2029 — a trajectory that analysts say could make the country a net electricity exporter to Uganda and Tanzania through the evolving East African Power Pool before the end of the decade.

Read More
SGR Posts First-Ever Operating Surplus as Luxury Coaches Roll Out
Energy & Transport

SGR Posts First-Ever Operating Surplus as Luxury Coaches Roll Out

Kenya Railways Corporation has announced the rollout of luxury first-class passenger coaches on the Standard Gauge Railway, with full operational deployment targeted by July 2026 — an upgrade that arrives alongside a landmark commercial milestone: the SGR has recorded its first-ever operating surplus.

First Operating Surplus and the Luxury Coach Announcement

KRC officials described the surplus as evidence that the line’s passenger numbers, freight volumes, and ticketing revenues have finally crossed the threshold required to cover direct operational expenditures. KRC’s overall financial position has remained stressed, with corporate losses widening to Sh28 billion — partly a legacy of the old metre-gauge railway network. The new luxury first-class coaches are designed to elevate the passenger experience beyond existing business and economy classes.

What Comes Next

KRC and the State Department for Transport must address the structural challenge that the SGR’s operating surplus cannot offset: the Sh28 billion corporate loss driven largely by MGR liabilities and legacy costs.

Read More
KenGen Olkaria Expansion at 70% as Turbine Commissioning Nears
Energy & Transport

KenGen Olkaria Expansion at 70% as Turbine Commissioning Nears

Kenya Electricity Generating Company (KenGen) has reported that its Olkaria I geothermal expansion project in the Great Rift Valley has reached 70 percent completion on key milestones, with the company expressing confidence that the first turbine will be commissioned by June 2026, adding 63 megawatts of clean baseload power to Kenya’s national grid.

70% Completion and the Path to First Turbine Commissioning

KenGen disclosed in June 2026 that the Olkaria I expansion had cleared 70 percent of its key project milestones. “We are on course to bring the first turbine online within our targeted window,” said a KenGen official. Geothermal plants operate at very high capacity factors — often above 85 percent — compared with intermittent renewables such as wind and solar.

What Comes Next

Following commissioning of the first turbine, KenGen and KETRACO must complete grid-connection testing and synchronisation before commercial generation begins. KenGen has signalled further expansion ambitions at additional Rift Valley sites.